Voters passed a bond measure in 2018 to fund improvements across the entire district, including at Four Corners Elementary School. Bond funding will provide nearly $6 million in additions and improvements at Four Corners.

Highlights of the work planned at Four Corners include:
• Five new classrooms
• Removal of portable classrooms
• Music room improvements
• Seismic improvements
• Electronic badge access system upgrades
• Kitchen improvements
• Roofing replacement
• Increased visibility of the main entry from the office, including a secured vestibule

The district’s project management team is currently working with Anderson Shirley Architects to finalize the drawings that construction contractors will use to add and improve the spaces at Four Corners.

Construction is scheduled to begin in the summer of 2022 and is expected to be complete early in the fall of 2023.

For more information about bond-funded construction projects in Salem-Keizer Public Schools, please visit the Bond Projects home page.

Thank you, voters!